BUSINESS CENTRAL SAAS REIMPLEMENTATION

Overview

Controlled reimplementation · Target go-live June 2027

Programme on track
↗
OVERALL PROGRESS24%

Mobilisation underway

◇
NEXT MILESTONEScope baseline

30 Sep · 50 days

△
OPEN RAID ITEMS7

3 high priority

✓
GO-LIVE GATES0 / 7

Readiness starts May

Programme plan

6 phases · Aug 2026 - Aug 2027

1Mobilisation & scope refreshAug - Sep 2026
36%
2Solution confirmationSep - Oct 2026
8%
3Build & data preparationOct 2026 - Feb 2027
0%
4Rehearsals & testingFeb - Apr 2027
0%
5Readiness & go-liveMay - Jun 2027
0%
6Hypercare & transitionJun - Aug 2027
0%

Priority work

Items needing focus now

Go-live readiness

Mandatory acceptance gates

0 of 7 complete

Recent activity

Latest programme updates

VB

Vince Blackhall updated the delta inventory10 min ago

RR

Ryan Riddell flagged Commidea as blocked42 min ago

SK

Sarah Kay added 4 workstream deputiesYesterday